(in Polish)
Michał Krzemiński
Volume 526; Issue 6
Pages 27-28
Accepted for publication: 04.04.2016 r.
The article presents a newly developed model for minimising construction team downtime. The model is designed specifically for construction schedules created with the assumption that the work will be organised in accordance with the Linear Scheduling Method (LSM). Such schedules are utilised in the construction industry in cases of structures that can or should be subdivided and it is expected that the subsequent work processes carried out on the subdivisions will be organised in accordance with the technological assumptions. The example of usewas also presented.
Keywords: flowshop model; minimum slack; scheduling; construction scheduling
Keywords: flowshop model; minimum slack; scheduling; construction scheduling
- Hejducki Zdzisław. 2003. „Scheduling model of construction activity with time coupulings”. Journal of Civil Engineering and Management 9 (4): 284 – 291.
- Krzemiński Michał. 2014. Use of the KASS program in scheduling. Technical Transaction 2-B (6): 217 – 224.
- Pinedo Michael. L. 2012. Scheduling. Theory, Algorithms and Systems. Springer.
- Rogalska Magdalena, Wojciech Bożejko, Zdzisław Hejducki. 2008. „Time/cost optimization using hybrid evolutionary algorithm in construction project scheduling”. Automotion in Construction 18: 24 – 31.
Michał Krzemiński, Ph. D. Eng. - Warsaw University of Technology, Faculty of Civil Engineering
Michał Krzemiński, Ph. D. Eng.
Full paper is available at Publisher house SIGMA-NOT Sp. z o.o. webpage