Examples of using requirements for construction of nuclear power facilities


Vol. 544 (12) 2017 / wtorek, 30 października, 2018

(in Polish)

T. Piotrowski,
P. Prochoń

DOI: 10.15199/33.2017.12.25

Volume 544; Issue 12
Pages 84-85

Accepted for publication: 03.11.2017 r.

The paper presents European examples of the use of requirements for construction of structures in nuclear power facilities. It contains experience in implementing foreign or international detailed requirements in ongoing nuclear projects in Sweden, France, Finland and United Kingdom. The quoted examples show that regardless of the adopted scenario, it is a very complex, expensive and long-term process that requires cooperation of many environments. This is very important from the implementation of the Polish Nuclear Power Program point of view. As announced by the Ministry of Energy its update will be relayed to the Council of Ministers by the end of 2017.

Keywords: standards; guidelines; nuclear power plant; reactor containment of concrete.
  1. Piotrowski Tomasz. 2013. „Wymagania dotyczące betonu w elektrowni jądrowej typu EPR wg ETC-C a normalizacja w Polsce”. Materiały Budowlane 5 (489): 35 – 38.
  2. Piotrowski Tomasz, M. Maslakowski, R. Kuszyk R. 2014. „Budowa elektrowni jądrowej w Polsce w świetle wymagań ETC-C i innych standardów technicznych na świecie/Construction of a nuclear power plant in Poland according to ETC-C and other technical guidelines in the world”. Materiały Budowlane 5 (501): 88 – 90;
  3. Piotrowski Tomasz. 2016. „Wymagania RCC-CW dotyczące betonu do budowy elektrowni jądrowych PWR w świetle PN-EN 206: 2014/RCC-CW requirements on concrete in the construction of PWR nuclear power plants in the light of the PN-EN 206:2014”. Materiały Budowlane 529 (9): 89 – 91; (B-8). DOI: 10.15199/33.2016.09.35.
  4. Piotrowski Tomasz, Andrzej Garbacz, Piotr Prochoń. 2017. Konstrukcje z betonu w obiektach energetyki jądrowej/Concrete Structures in Nuclear Power Plants. Politechnika Warszawska, Wydział Inżynierii Lądowe. ISBN 978-83-948948-0-1.
  5. RCC-CW 2015, Rules for Design and Construction of PWR nuclear civil works, AFCEN 2015.
Tomasz Piotrowski, Ph. D. Eng. - Warsaw University of Technology, Faculty of Civil Engineering

Piotr Prochoń, MSc. Eng. - Warsaw University of Technology, Faculty of Civil Engineering

Tomasz Piotrowski, Ph. D. Eng.

t.piotrowski@il.pw.edu.pl

Full paper is available at Publisher house SIGMA-NOT Sp. z o.o. webpage

DOI: 10.15199/33.2017.12.25